IAH Terminal D: Checkpoint Remodel
- Project Budget: $3.5 million
- Project Start: January 2017
- Estimated Completion: January 2018
- Description: Complete remodel of checkpoint including reconfiguration of existing lanes and addition of one lane with automated bin return system.
- Photo: [Placeholder for Checkpoint Remodel Photo]
EFD (Ellington Airport): New Air Traffic Control Tower
- Project Budget: $11 million
- Project Start: April 2017
- Estimated Completion: September 2018
- Description: Replacement of existing air traffic control tower with a new tower to enhance services and support Houston Spaceport operations.
- Photo: [Placeholder for New Air Traffic Control Tower Photo]
IAH Terminal D: Baggage Makeup Units
- Project Budget: $4 million
- Project Start: November 2015
- Estimated Completion: December 2017
- Description: Complete remodel of baggage handling system including demolition and reconstruction of east baggage makeup units.
- Photo: [Placeholder for Baggage Makeup Units Photo]
IAH Terminal D: Restrooms
- Project Budget: $3.0 million
- Project Start: May 2017
- Estimated Completion: May 2018
- Description: Remodel of existing restrooms at D6, D7, ticketing level East and West, introducing new concepts with modular wall panel systems.
- Photo: [Placeholder for Restrooms Remodel Photo]
EFD (Ellington Airport): Scholl Road Reconstruction
- Project Budget: $2.4 million
- Project Start: March 2017
- Estimated Completion: December 2017
- Description: Reconstruction of Popa Street, Nelson Avenue, and Scholl Road to a 30-year pavement design standard.
- Photo: [Placeholder for Scholl Road Reconstruction Photo]
IAH: Advanced Parking Guidance System
- Project Budget: $15.3 million
- Project Start: September 2017
- Estimated Completion: March 2019
- Description: Implementation of advanced parking guidance system in parking garages to improve customer experience.
- Photo: [Placeholder for Advanced Parking Guidance System Photo]
IAH: Residential Noise Insulation Program - Phase I
- Project Budget: $1.9 million
- Project Start: December 2017
- Estimated Completion: November 2018
- Description: Construction program to reduce aircraft noise in 27 single-family homes with new windows, doors, and insulation.
- Photo: [Placeholder for Residential Noise Insulation Program Photo]
IAH Terminal D: Sales & Check-in Counters
- Project Budget: $2 million
- Project Start: May 2016
- Estimated Completion: March 2018
- Description: Demolition of existing and installation of new ticket and gate check-in counters with upgraded scales, alert monitors, lighting, carpeting, and ADA accessibility.
- Photo: [Placeholder for Sales & Check-in Counters Photo]